Most loads move under what the law already allows. Some do not, and the moment yours crosses a line, the job changes: it needs a permit, and sometimes a route, a time window and a sign on the back. Here is where the lines are in Ontario and what happens once you cross one.
The legal limits
Ontario sets these in the Highway Traffic Act, section 109. Below them, no oversize permit is needed. Above any one of them, you need one.
- Width: 2.6 m, vehicle including the load
- Height: 4.15 m, vehicle including the load
- Length, semi-trailer including load: 16.15 m for SPIF-designated vehicles, 14.65 m for non-SPIF
- Length, whole combination including load: 23 m
Note what the width and height limits are measured on: the vehicle including its load. The deck itself has height. A machine that is 3.9 m tall on the ground is not 3.9 m tall once it is sitting on a flatbed, and that is the number that matters at an overpass.
Weight is a separate question
Overweight permits work on their own rules — axle configuration, spacing and the season. Ontario also runs reduced load periods in spring, when thawing ground means certain roads carry less than they do the rest of the year. A load that is routine in August can need different handling in March on the same route.
What having a permit actually means
A permit is not simply a receipt that makes the problem go away. Depending on the load it can come with:
- A specified route. Not the fastest way — the way that clears the bridges.
- Time-of-day restrictions. Many oversize moves are kept off the road at rush hour, and some are daylight-only.
- Signs and flags. Oversize Load signage, flags on the corners, sometimes lights.
- Escort vehicles. Wider loads need a pilot car, and the widest need more than one.
- A day of the week. Some permits exclude weekends and holidays.
Each of those costs time or money or both, which is why an oversize move is quoted differently from a standard one, and why it cannot be arranged in an hour.
Municipal roads are not covered by the provincial permit
This catches people out. A provincial permit covers provincial highways. If your pickup or delivery sits on a municipal road — and almost every one does at each end — the municipality may require its own permit. In this part of the province that can mean the City of London, Middlesex County, Oxford County, Elgin County, Lambton County or Chatham-Kent, depending on where the load starts and finishes.
Plan for the possibility of two permits, not one.
How to tell early whether you have an oversize load
Before you call anyone, measure. Not the spec sheet — the actual machine, with whatever is bolted to it right now.
- Widest point, including mirrors, buckets turned sideways, or anything sticking out
- Highest point, as it sits
- Overall length, including any attachment hanging off either end
- Operating weight, with attachments and with fluids
Then add the deck height to your height figure. If any number lands close to the limits above, say so when you call. Close is as important as over — a load at 2.55 m wide is legal, but it changes how carefully the route has to be chosen.
What usually needs a permit around here
In practice, the loads that most often cross a line in Southwestern Ontario are wide farm equipment, larger excavators with the boom in place, tall tanks and silos, prefabricated structures, and long steel or pipe. Most skid steers, mini excavators, compressors, pallets of material and vehicles move legally with no permit at all.
Not sure which one you have?
Call with your measurements and we will tell you plainly whether it is a standard move or a permitted one, before any money is discussed. 647-994-1074, seven days a week, 7am to 9pm.
Goraya Transportation Inc. is a flatbed carrier based in London, Ontario, running 22 ft and 19 ft decks across London, St. Thomas, Woodstock, Ingersoll, Strathroy, Sarnia and Chatham-Kent.
The dimensions above are the provincial limits under the Highway Traffic Act at the time of writing. Permit requirements, routes and municipal rules change. For anything you are relying on, confirm with the Ontario Ministry of Transportation and the municipality involved.